The project
A regional logistics business serving central Scotland approached us in late 2024. Their warehouse — a typical pre-fab 2,400m² industrial unit — had 1,800m² of south-east-facing roof and was paying around £180,000/year for electricity (refrigerated zones + extensive forklift charging).
Feasibility delivered in 4 weeks. SP Energy Networks G99 application running in parallel. 180kWp install completed across two weeks. CapEx route — capital allowances claimed in the same financial year (~£60,000 tax saved).
Year-one performance has matched modelling within 4%.
Results
Results are specific to this property. Savings depend on the customer's usage patterns, the system's generation and energy prices at the time of install, so your own figures will differ.
Free quote in 24 hours.
No high-pressure sales. No commission-driven scripts. Just a no-obligation survey + transparent quote — covering every postcode in Scotland's Central Belt.